The Padma Bridge is Bangladesh's longest bridge — a 6.15 km two-level steel truss carrying a four-lane highway and a railway across the Padma River. Built entirely with the government's own funds after the World Bank withdrew in 2012, it opened to road traffic on 25 June 2022 and to trains in 2023. This article covers its design, cost, tolls, traffic and economic impact.
Table of contents [Show]
The Padma Bridge is a 6.15-kilometre multipurpose bridge across the Padma River in Bangladesh — the country's longest bridge and, when it opened, its largest infrastructure project. It is a two-level steel truss bridge: a four-lane highway runs on the upper deck and a single-track railway on the lower. It connects Louhajang in Munshiganj district, at the Mawa end, with Zazira in Shariatpur and Shibchar in Madaripur, at the Jajira end, joining Dhaka directly to the country's southwestern region for the first time.
The bridge was inaugurated on 25 June 2022 by Prime Minister Sheikh Hasina and opened to road traffic the next day; trains began crossing in October 2023. It cost about Tk 30,193 crore to build, a figure that completion accounts later placed at Tk 30,770 crore — and every taka of it came from the Government of Bangladesh, after the World Bank and the project's other foreign financiers withdrew in 2012 amid a corruption allegation that was never proven in court. That history, as much as the structure itself, is why the Padma Bridge occupies a unique place in Bangladesh's public life: it is simultaneously an engineering work, a transport artery that transformed the southwest, and a national symbol of self-reliance. By its fourth anniversary in June 2026, about 26.9 million vehicles had crossed it, paying Tk 3,429 crore in tolls.
The Padma — the name the Ganges takes inside Bangladesh — is one of the world's great rivers, and at the Mawa–Jajira crossing it is wide, fast and unstable, shifting its channels and devouring its banks. The 21 southwestern districts it separates from Dhaka and the east are home to tens of millions of people and to Mongla, the country's second seaport, yet for decades their only connection to the capital was by water.
The crossing depended on ferries at Mawa that were slow, weather-bound and overwhelmed. Trucks queued for hours, sometimes days, on both banks; perishable goods rotted in the queue; patients died on the way to Dhaka's hospitals. A bridge at Mawa was studied repeatedly from the 1990s, and a feasibility study completed in the mid-2000s made the case formally: no single project would do more to integrate the national economy. The design that emerged — road above, rail below, with gas, power and fibre-optic lines carried across as well — was deliberately multipurpose, and the project was placed with the Bangladesh Bridge Authority.
The project nearly died a decade before it opened. In 2011 the World Bank committed US$1.2 billion towards the bridge, with the Asian Development Bank, the Japan International Cooperation Agency and the Islamic Development Bank also pledged. On 29 June 2012, the World Bank cancelled its credit, saying it had "credible evidence" of a "high-level corruption conspiracy" involving Bangladeshi officials, executives of the Canadian engineering firm SNC-Lavalin and private individuals in the award of a consultancy contract. The other financiers followed the Bank out. The communications minister, Syed Abul Hossain, resigned; SNC-Lavalin eventually accepted a settlement barring it from World Bank bidding for ten years.
The aftermath undercut the allegation itself. Bangladesh's Anti-Corruption Commission investigated and reported finding no evidence of the conspiracy, and in February 2017 a Canadian court excluded the wiretap evidence on which the prosecution rested; the charges were dropped and the accused executives acquitted. No corruption was ever proven in any court — but by then the question had been settled politically years earlier. Refusing to plead for the loans' return, Sheikh Hasina's government announced that Bangladesh would build the bridge with its own money.
The money was arranged as a domestic loan: the Finance Division lent the Bangladesh Bridge Authority Tk 29,893 crore at 1 percent interest, repayable over 35 years in 140 quarterly instalments — Tk 36,000 crore in total including interest. Tolls were assigned to service the debt, and by 30 June 2026 the Authority had repaid 16 instalments totalling Tk 2,516.68 crore, in addition to Tk 436.08 crore paid as value-added tax on toll income.
The Padma is a difficult river to bridge, and the structure reflects that. Its 6.15 kilometres are carried on 41 spans of 150.12 metres each, supported by 42 piers. Each pier stands on six steel piles driven into the riverbed to depths of up to about 127 metres — the deepest foundation piles of any bridge in the world, a necessity in a river whose bed is deep, soft and constantly scoured by monsoon flows. The steel truss superstructure, 18.10 metres wide, was designed by an international team led by AECOM.
The two-level arrangement is the bridge's defining feature. The upper deck carries a four-lane highway, part of the Dhaka–Bhanga Expressway and the Asian Highway network. The lower deck carries a single broad-gauge railway track, built into the structure from the start even though the railway line itself was a separate project that arrived later. The bridge also carries a gas transmission pipeline, high-voltage electricity lines and optical-fibre and telephone ducts, so that the day it opened, the southwest was connected to the capital by energy and data as well as by road.
One point of persistent confusion is worth settling: despite its elegant silhouette, the Padma Bridge is not a cable-stayed bridge. No cables hold its deck. It is a steel truss — a rigid lattice of steel members — resting on its 42 piers, a design chosen for the loads of a combined road-and-rail crossing on a soft riverbed.
Construction contracts were let in 2014. The main bridge went to China Major Bridge Engineering Co. Ltd, which emerged as the sole financial bidder among four shortlisted firms; work on the main structure began on 26 November 2014. River training — the immense task of stabilising the banks and guiding the river through the crossing with dredging and protective works — was awarded to China's Sinohydro, and the approach roads and service areas to Bangladesh's Abdul Monem Ltd.
The milestones came slowly, against a river that flooded, eroded and repeatedly changed course around the works. The first span was installed in October 2017, between piers 37 and 38. All 42 piers were complete by 27 November 2020, and the final, 41st span was set in place on 10 December 2020, joining the two banks for the first time. The last road slab was laid on 24 August 2021, and construction formally ended on 23 June 2022 — two days before the inauguration.
The cost, meanwhile, had roughly tripled from the earliest estimates: about Tk 10,161 crore in 2007, Tk 20,507 crore in the 2011 revision and Tk 28,793 crore by 2016, before settling at Tk 30,193.39 crore at opening. When the project was declared complete on 30 June 2024, the Bridge Authority put the final cost at Tk 30,770.13 crore, against a revised allocation of Tk 32,605.51 crore.
Sheikh Hasina inaugurated the bridge on 25 June 2022 before a crowd of hundreds of thousands at both ends, and was herself the first to cross, paying the Tk 750 toll for her car. Public traffic began at 6:00 am on 26 June. In the first eight hours about 15,200 vehicles crossed, paying Tk 82.19 lakh; on 1 July 2022 the bridge set an early record of 26,394 vehicles and Tk 3.16 crore in a single day. Motorcycles, initially barred over safety fears, were admitted in time for the Eid rush, and electronic toll collection has since been introduced at both ends.
Tolls, fixed by a Bridges Division gazette of 17 May 2022 and charged one-way, are steep by local standards but reflect the ferry costs and delays they replaced:
The traffic has justified the road, if not yet the most optimistic forecasts. In its first year, to 23 June 2023, 5.654 million vehicles crossed — an average of more than 15,000 a day — paying Tk 794.53 crore in tolls. By 29 June 2026, the fourth anniversary, the cumulative figures stood at 26,862,808 vehicles and Tk 3,429.45 crore in tolls, an income stream that now services the government's construction loan on schedule. The contrast with the country's other great crossing, the Karnaphuli Tunnel in Chittagong, which has struggled to attract a seventh of its projected traffic, is instructive: the Padma crossing replaced a bottleneck everyone already had to use, while the tunnel had to compete with an existing bridge.
The railway in the bridge's lower deck is part of a separate and larger project: the Padma Bridge Rail Link, a 169-kilometre line built by Bangladesh Railway from Dhaka to Jashore via Bhanga, Faridpur and Narail. The line cost Tk 39,246.80 crore, of which Tk 21,036.70 crore came as a loan from the Export-Import Bank of China, and it was built by the China Railway Group under a government-to-government arrangement. It has 20 stations, 14 of them newly built, and its construction began in 2018.
A trial train crossed the bridge from Bhanga on 4 April 2023. The first section, the 82 kilometres from Dhaka to Bhanga, was inaugurated on 10 October 2023, with commercial passenger services starting on 1 November 2023 — the first trains in history to cross the Padma. The full line to Jashore opened on 24 December 2024, cutting the Dhaka–Jashore journey from about ten hours to about three, with Dhaka–Khulna taking about three hours forty-five minutes. For the southwest, which had been effectively cut off from the national railway network by the river, it is the bridge's second revolution.
The bridge was appraised, before construction, as one of the highest-return investments available to Bangladesh. The World Bank's assessment projected that it would raise national GDP by about 1.23 percent and the GDP of the southwestern region by about 2.3 percent, and reduce poverty by 0.84 percentage points nationally and 1.01 points in the southwest. Economists at the Centre for Policy Dialogue estimated in June 2022 that the bridge's benefits over its economic life would exceed US$10 billion — more than three times its cost — counting journey times cut by about two hours for cars and buses and more than ten hours for trucks that once queued for ferries.
Four years on, the visible changes match the direction of those forecasts. Journeys from Dhaka to Khulna and Barisal that consumed a day now take four hours or less. Mongla Port's cargo volumes have grown as its hinterland gained a land route to the capital. Land values and industrial plots in the southwest have risen, the government has planned 17 economic zones in the region, and the gas, power and fibre connections carried across the bridge have reached districts that previously depended on fragile local supply. Rigorous ex-post studies of the GDP claims will take years, and the figures above remain projections; but the integration itself is not in dispute.
The losers were the ferries. The Mawa crossing had run nine ferries on the shortest route, alongside 87 launches and 155 speedboats making more than 300 trips a day between them. On the bridge's first day, no ferry sailed from Shimulia towards Majhirkandi, launch and speedboat trips collapsed to about 70, and two ferries were transferred to the Aricha route within days. By August 2022, the State Minister for Shipping told parliament that every one of the 87 launches and 155 speedboats on the Shimulia routes had stopped, the Mawa–Majhirkandi ferry service had ceased, and Dhaka's Sadarghat had lost a quarter of its southern launches. An entire river economy of ghats, vendors, boatmen and transport workers had to find new work — the necessary, and largely unexamined, cost of the bridge's success.
The bridge's problems are those of a victim of its own centrality. Maintenance of a 6.15-kilometre steel structure in one of the world's most aggressive river environments is a permanent and expensive obligation; river training must continue indefinitely to keep the Padma in its channel. The approaches concentrate traffic onto roads that must keep pace, and the debt — Tk 36,000 crore with interest — binds toll income to the Finance Division loan until the 2050s. The tolls themselves are politically sensitive: high enough to service the debt, they are periodically attacked as a tax on the southwest.
None of this has displaced the bridge from its place in national life. The Padma Bridge proved that Bangladesh could finance and build a world-scale structure alone, after being told it could not — and the trains now running beneath its roadway, three hours from Dhaka to Jashore, complete the connection its designers promised in 2007. Assessed on the evidence of its first four years — 26.9 million vehicles, Tk 3,429 crore in tolls, a region reconnected — it stands as the most consequential piece of infrastructure in the country's history, and the standard against which every later megaproject, including the Karnaphuli Tunnel, is now measured.
Agriculture in Bangladesh employs 45% of workers and grows 40.6 million tonnes of rice — its output, tiny farms, subsidies, imports and climate risks.
Bangladesh's national fish supplies most of the world's hilsa and about 1% of GDP — its production, conservation bans, Chandpur trade and India exports.
Migration and remittance now rival garments as Bangladesh's economic engine: record inflows, the world's highest migration costs, and the risks workers face.