The Rooppur Nuclear Power Plant at Ishwardi, Pabna is Bangladesh's first nuclear power station: two Russian-built VVER-1200 reactors with a combined capacity of 2,400 MW. First proposed in 1961, its first unit achieved criticality in October 2026. Its history, cost, commissioning status and debates.

On the east bank of the Padma River at Rooppur, in Ishwardi upazila of Pabna district, stands the largest single power project in Bangladesh's history: two Russian-designed VVER-1200 reactors with a combined capacity of 2,400 megawatts. The Rooppur Nuclear Power Plant has been under construction since 2017, but the idea behind it is far older — it was first proposed in 1961, when Bangladesh was still East Pakistan. In October 2026, sixty-five years after that first proposal, the plant's first reactor achieved a self-sustaining nuclear chain reaction for the first time. As of November 2026, Unit 1 is in the power start-up stage of commissioning, and project officials say its first electricity — an initial trial supply of about 300 MW — could reach the national grid within weeks. This article traces how the plant came to be, what it costs, exactly where commissioning stands, and the arguments that continue to surround it.

A Sixty-Year-Old Idea

In 1961 the Pakistan Atomic Energy Commission proposed a nuclear plant for East Pakistan, and in 1963 Rooppur — a riverside site about 160 kilometres north-west of Dhaka — was selected, with about 260 acres (105 hectares) of land acquired. The project was approved at 70 MW in 1963, 140 MW in 1966 and 200 MW in 1969, the last plan worked out with Belgian assistance. It was never built. Between 1969 and 1971 the Pakistan government shelved Rooppur and gave priority to Karachi, where a Canadian-supplied reactor — of a type once considered for Rooppur — was completed instead.

Independent Bangladesh revived the idea repeatedly without ever financing it. The Bangladesh Atomic Energy Commission (BAEC) was created in 1973, an IAEA-reviewed French proposal for a 125 MW plant was judged suitable in the late 1970s, and the Executive Committee of the National Economic Council approved a 125 MW scheme in 1980, only for it to lapse when financing fell through. A national Nuclear Power Action Plan followed in 2000, and fresh BAEC proposals in 2007. The breakthrough came through diplomacy: a memorandum of understanding with Russia's Rosatom on 13 May 2009, a framework agreement in 2010, and an IAEA Integrated Nuclear Infrastructure Review mission in 2011. On 2 November 2011 the two governments signed the intergovernmental agreement under which Russia would build the plant at Rooppur — fifty years after the site was first chosen for exactly that purpose.

The Russian Deal and the Design

The commercial structure was assembled in stages. A Russian state credit of US$500 million, agreed in January 2013, financed preparatory works. On 25 December 2015 BAEC signed the general contract with Atomstroyexport, the engineering arm of Rosatom, worth US$12.65 billion for the design, construction and commissioning of both units. The main Russian state credit — US$11.38 billion, covering 90 percent of the contract price — was signed on 26 July 2016, at an interest rate of LIBOR plus 1.75 percent, capped at 4 percent, repayable over 28 years with a ten-year grace period; Bangladesh funds the remaining 10 percent. In taka terms the project was approved at about Tk 1,13,092 crore. Because the loan is denominated in dollars while the taka has depreciated sharply, officials proposed a revision in 2025 that would raise the taka cost to about Tk 1,39,274 crore — roughly 23 percent higher — and extend the project deadline to June 2028, even though the dollar price is unchanged.

Each unit is a VVER-1200 of the AES-2006 design, a Generation III+ pressurised water reactor of the kind Russia has built at Novovoronezh and Leningrad II. Each produces 1,200 MW of electricity, giving the station its 2,400 MW total, and the design working life is 60 years. The safety concept layers active systems over passive ones that need no electrical power to function, inside a double containment structure; beneath the reactor vessel sits a "core catcher", a device designed to contain the molten core in a severe accident. The plant draws cooling water from the Padma — the name taken by the Ganges as it flows through Bangladesh, one of the great rivers of Bangladesh. BAEC is the project owner, the Nuclear Power Plant Company Bangladesh Limited (NPCBL), formed in 2015, is being prepared as the operating organisation, and licensing rests with the Bangladesh Atomic Energy Regulatory Authority (BAERA), which issued the site licence in June 2016 and the design and construction licence for Unit 1 in November 2017.

Building the Plant

Main construction began with the first concrete of Unit 1 on 30 November 2017; Unit 2 followed on 14 July 2018. The heavy milestones of the nuclear island came in sequence: the reactor pressure vessel of Unit 1 was installed in October 2021 and that of Unit 2 in October 2022, and concreting of Unit 1's outer containment was completed in March 2023. At its peak the site employed tens of thousands of workers, the majority of them Bangladeshi, alongside a large Russian specialist workforce housed in a purpose-built residential area known as Green City. Bangladeshi engineers and operators have been trained in Russia, including at Novovoronezh, the VVER-1200 reference plant.

The schedule slipped repeatedly. The original targets — Unit 1 in commercial operation in 2023 and Unit 2 in 2024 — were pushed back by the COVID-19 pandemic, by supply-chain disruption following Russia's invasion of Ukraine, and by difficulties in making payments through sanctioned Russian banking channels. A revised schedule agreed in June 2025 set commercial operation for Unit 1 in December 2026 and for Unit 2 in December 2027. The delays have a price: Bangladeshi commentators have noted that interest accrues on the Russian credit throughout, and the taka cost has climbed with the exchange rate even as the dollar cost stayed fixed.

Where Commissioning Stands Now: November 2026

Unit 1 has now crossed the line from construction project to operating nuclear facility. Fresh nuclear fuel for the plant first arrived in Bangladesh in October 2023 and was formally received at the site on 5 October 2023; the full initial core for Unit 1 was delivered that autumn and held in storage while pre-commissioning tests — including cold and hot functional testing — were completed during 2025. On 16 April 2026 BAERA issued the commissioning licence for Unit 1. Fuel loading began on 28 April 2026, and by mid-May all 163 fuel assemblies had been placed in the core, as The Business Standard reported on 12 May 2026.

The next regulatory step took longer than planned. BAERA's approval for the first-criticality stage was held up for weeks by complications involving the reactor's pilot-operated pressure relief safety valves, as the state news agency BSS reported on 8 October 2026; Bangladeshi and Russian specialists worked jointly on the problem. BAERA gave its approval on 8 October, and on 11 October 2026, at 3:34 p.m., Unit 1 achieved first criticality — a controlled, self-sustaining chain reaction. Physics tests at minimum controllable power followed, and on 29 October 2026 BAERA cleared the unit to enter Stage C, power start-up, in which reactor power is raised in steps and the turbine-generator is prepared for synchronisation. By early November the reactor had reached about 20 percent of thermal power, according to the science and technology minister, Fakir Mahbub Anam.

As of mid-November 2026 the plant stands at the threshold of generation. The Business Standard and BSS reported on 15 November 2026 that preparations for synchronising Unit 1 with the national grid were under way and that, subject to BAERA's trial-operation approval and successful tests, an initial supply of around 300 MW could begin within November; the authorities plan a formal inauguration of the initial generation in December. BAERA's chairman, Mahmudul Hasan, has cautioned that no exact date can be confirmed in advance. Officials expect output to climb over the following months — past 1,100 MW within roughly the first six months and to the full 1,200 MW by around April 2027 — with the unit's commercial operation formally targeted for December 2026 under the revised schedule, so the formal milestone and the physical ramp-up overlap into 2027.

Unit 2 is roughly a year behind its sister. Its construction is at an advanced stage, with its reactor vessel installed since 2022, and its fuel is now arriving: the first consignment of Unit 2 fuel assemblies reached Bangladesh on 3 October 2026, and Rosatom is delivering all 163 assemblies in seven flights between October and December 2026 — six shipments had arrived by mid-November, according to the Daily Observer — while preparations for the unit's initial fuel loading advance. Commissioning of Unit 2 is expected to follow through 2027, with commercial operation targeted for December 2027 and overall project completion by June 2028.

Fuel and Waste

Russia supplies Rooppur's fuel as well as its reactors. The fuel is manufactured by TVEL, Rosatom's fuel company, under contracts tied to the project; fresh fuel for Unit 1's first refuelling has already been delivered alongside the Unit 2 consignments in late 2026. Refuelling takes place in partial batches during planned outages, so deliveries will continue for the plant's working life.

The spent-fuel question — for decades the strongest objection to nuclear power in a densely populated delta — is addressed by a take-back arrangement unusual among newcomer nuclear states. On 30 August 2017 Bangladesh and Russia signed an intergovernmental agreement in Moscow under which spent fuel from Rooppur will be returned to Russia for reprocessing, recycling and management of the resulting products. Officials said at the time that shipments, by sea, were envisaged every five to seven years once the plant is in commercial operation, with the detailed commercial terms of removal to be settled in follow-on contracts — a point critics continue to note, since those implementing arrangements have yet to be concluded. Meanwhile, spent fuel is cooled and stored at the plant under BAERA regulation.

Power for the Grid

A nuclear plant is only as useful as the wires leaving it, and Rooppur's output required a dedicated evacuation network built by Power Grid Bangladesh PLC: some 669 kilometres of new lines — 464 kilometres at 400 kV and 205 kilometres at 230 kV — financed largely through a US$1.06 billion Indian line of credit agreed in 2017. The 230 kV Rooppur–Baghabari line was completed in April 2022 and the 400 kV Rooppur–Bogura line in April 2024; the 400 kV Rooppur–Gopalganj line was energised on 2 June 2025, and remaining sections, including the Rooppur–Dhaka connection, have been carried forward under a revised transmission project whose cost was cut to Tk 86.52 billion with a completion deadline of June 2026, as The Financial Express reported in May 2026.

At full output the two units will supply about a tenth of Bangladesh's electricity — firm, weather-independent baseload in a system whose gas fields are depleting and which has leaned heavily on imported fuel. That promise is not yet fully priced: as the Power Division pointed out in 2025, the power purchase agreement and tariff for Rooppur's electricity were still being finalised years after construction began, and officials have warned that the tariff decision will determine how much of the plant's cost lands in electricity subsidies. The same river system that cools the plant also carries the Padma Bridge downstream — the two projects together mark how thoroughly Bangladesh's recent development has been staked on megaprojects along the Padma.

Safety and Debate

Rooppur has been licensed in stages, and the commissioning record of 2026 shows the regulator using that leverage: BAERA withheld the first-criticality approval for weeks over the safety-valve issue and has cleared each stage — fuel loading, criticality, power start-up — separately. The IAEA has been involved since the 2011 infrastructure review, and in August 2025 an IAEA pre-OSART mission reviewed Unit 1's readiness for operation. Bangladeshi press coverage of that review, and commentary by specialists such as University of Dhaka nuclear engineering professor Md Shafiqul Islam, reported shortcomings in areas including safety-culture practice and staff preparation; project officials respond that the staged licensing process exists precisely to close such findings before power is raised, and that no stage proceeds without BAERA's consent.

The economic debate is sharper. Critics — among them energy analysts and IEEFA-linked commentary — argue that the plant locks Bangladesh into two decades of foreign-currency debt service for power whose estimated generation cost has risen from about Tk 6 per unit in 2023 projections to around Tk 10 at 2026 exchange rates, and that cheaper solar capacity was neglected in the meantime. The Foreign Aided Project Audit Directorate has flagged financial irregularities of about Tk 29,600 crore across nine years of project spending, as reported by the Daily Observer in 2026, and the Anti-Corruption Commission opened an investigation into procurement allegations in late 2024; the allegations remain under investigation and unproven. Supporters, including successive governments, answer that Bangladesh's gas reserves are running down, that the plant's fuel take-back deal removes the long-term waste burden borne by other nuclear programmes, and that 2,400 MW of low-carbon baseload — significant for a country central to the climate change debate — cannot be replicated by intermittent sources alone. Both the criticism and the defence are now being tested against the same evidence: whether the plant runs safely, reliably and at the promised cost.

What Happens Next

The immediate milestones are dated and public: trial grid supply from Unit 1, expected within November 2026; a formal inauguration of initial generation planned for December 2026; a staged climb to full power through the first months of 2027; and Unit 2's start-up sequence through 2027 towards commercial operation targeted for December 2027, with the project as a whole due for completion by June 2028. Beyond commissioning lie the quieter obligations of ownership: concluding the tariff and power purchase arrangements, finalising the spent-fuel shipment contracts, building NPCBL into a fully independent operator as Russian support tapers, and servicing the Russian credit, whose repayments run for two decades beyond its ten-year grace period.

Whatever judgement history passes on its cost and its controversies, Rooppur has already changed Bangladesh's position in the world: a country that waited sixty-five years between proposing a nuclear plant and splitting an atom for power is about to join the small group of states generating electricity from nuclear energy. The cooling towers on the Padma's bank — visible from the Hardinge Bridge that has crossed the river since 1915 — are the newest landmark of a much older ambition.