• 18 Nov, 2026

Dhaka Metro Rail's MRT-6 now carries over 450,000 passengers a day between Uttara and Motijheel. This profile covers the line's route, stations, fares and record ridership, the delayed Kamalapur extension due in 2027, and the MRT-1 and MRT-5 lines now under construction.

For decades, the defining experience of Dhaka was standing still: buses, cars, rickshaws and CNG auto-rickshaws locked together on avenues where the average journey could be measured in hours rather than minutes. The Dhaka Metro Rail changed that for one corridor of the capital, and it is changing the city's habits with it. Since the first trains ran in December 2022, the elevated MRT Line 6 has grown into the busiest single piece of transport infrastructure in Bangladesh. According to figures from the Dhaka Mass Transit Company Limited (DMTCL) reported in September 2026, more than 313.5 million passengers had ridden the line since its launch, daily ridership was running consistently above 450,000, and on 10 September 2026 the metro carried a record 499,756 passengers in a single day, very close to the half-million daily figure projected for it when the project was approved.

Yet the metro remains, for now, a single line in a city planned to have many. MRT-6 still ends one station short of its intended terminus at Kamalapur, and the two lines meant to follow it, the underground MRT-1 and the east–west MRT-5 Northern Route, have slipped years behind their original schedules even as their main construction contracts were finally signed in October 2026. This profile sets out how the metro was built, how the operating line works today, what it costs to ride, what it has changed, and what is realistically coming next.

How the Metro Was Built

A metro for Dhaka was first proposed in the Strategic Transport Plan of 2005, and the idea survived into the Revised Strategic Transport Plan of 2015, which envisaged a network of five mass rapid transit lines across the capital by 2035. The first line chosen was MRT-6, a north–south corridor from Uttara, the fast-growing suburb at the city's northern edge, through Mirpur, Farmgate and Shahbagh to the commercial district of Motijheel. The Executive Committee of the National Economic Council (ECNEC) approved the project in December 2012 at an estimated cost of Tk 21,985 crore, financed largely by loans from the Japan International Cooperation Agency (JICA). In June 2013 the government created the Dhaka Mass Transit Company Limited (DMTCL), a state-owned company under the Road Transport and Highways Division, to build and operate the network.

Construction began in 2016, starting with the depot at Diabari in Uttara, and the viaduct then advanced southwards above some of the most congested streets in the world. The trains, stainless-steel sets built in Japan by a Kawasaki–Mitsubishi consortium, run on standard-gauge track with platform screen doors, air-conditioned carriages and a fully elevated alignment. The first section, 11.73 kilometres from Uttara North to Agargaon with nine stations, was inaugurated on 28 December 2022 and opened to passengers the following day, making Bangladesh the third country in South Asia with a metro. The second section, from Agargaon to Motijheel, opened on 4 November 2023, completing the 20.1-kilometre, 16-station line that operates today.

The project did not stand still on paper while it was being built. A second revision, approved in July 2022, extended the line by 1.16 kilometres from Motijheel to Kamalapur and raised the budget to Tk 33,472 crore. A third revision in late 2025 trimmed the cost slightly, to Tk 32,717.72 crore, of which Tk 20,195.76 crore is JICA loan finance and Tk 12,521.96 crore government funding, and extended the project's completion period to December 2028. Even after the trim, the final cost stands about 49 per cent above the original 2012 estimate, a rise that frames much of the debate about the lines still to come.

MRT-6 Today: Route, Stations and Operations

The operating line runs 20.1 kilometres from Uttara North to Motijheel, entirely on elevated viaduct. Its sixteen stations, north to south, are Uttara North, Uttara Center, Uttara South, Pallabi, Mirpur 11, Mirpur 10, Kazipara, Shewrapara, Agargaon, Bijoy Sarani, Farmgate, Karwan Bazar, Shahbagh, Dhaka University, Bangladesh Secretariat and Motijheel. The alignment threads together the city's northern suburbs, the Mirpur corridor, the government quarter around Agargaon and Sher-e-Bangla Nagar, the university district, the Dhaka University station serves the campus of the University of Dhaka directly, and the old commercial heart at Motijheel. A full end-to-end journey takes about 35 minutes, a trip that can take two hours or more by road at peak times.

As of late 2026, trains run seven days a week. From Saturday to Thursday the first train leaves Uttara North at 6:30 am and Motijheel at 7:15 am, and the last trains depart at 9:50 pm from Uttara North and 10:30 pm from Motijheel. Fridays are different: to allow for the weekly day of prayer and for maintenance, services begin at 3:00 pm. Trains run every few minutes at the busiest times, around five minutes between services at peak, and less frequently early and late in the day. DMTCL has been adding trains and stretching operating hours in stages as ridership has climbed, and officials have said further extensions of hours are planned once the Kamalapur section opens.

The Kamalapur Extension

The line's final 1.16 kilometres, from Motijheel to a new station at Kamalapur, Dhaka's principal railway terminus, remain under construction as of November 2026. The extension was originally scheduled to open in June 2025, and its target has slipped repeatedly since. The most recent official position, given by the project director to the state news agency BSS on 17 October 2026 and reported in detail by Prothom Alo on 26 October, is that civil construction stood at 84.85 per cent complete as of 30 September 2026: the viaduct is finished and handed over for track installation, Kamalapur station's structure is complete, and mechanical, electrical and architectural works are due to finish by 31 December 2026. Trial runs are planned for February 2027, with commercial passenger services expected to begin in July 2027. When it opens, the extension will complete MRT-6 at 21.26 kilometres and 17 stations, connect the metro directly to intercity and commuter trains, and, on DMTCL's projection, lift daily ridership to about 677,000.

Fares and Passes

Fares on MRT-6 are distance-based, charged at Tk 5 per kilometre. The minimum fare is Tk 20, and the maximum, the full journey from Uttara North to Motijheel, is Tk 100. Passengers can buy a single-journey ticket at station counters or vending machines, but the system's regular users mostly travel on one of two stored-value smart cards: the MRT Pass, issued by DMTCL, and the Rapid Pass, the multi-operator card administered for use across public transport. Both cards give a 10 per cent discount on every metro fare, so the longest journey costs a cardholder Tk 90. A Rapid Pass costs Tk 400 to obtain, split between a Tk 200 refundable deposit and Tk 200 of travel balance, and both cards can be recharged at stations. There are no separate student or concession fares; the 10 per cent card discount is the only standing reduction the current fare structure offers.

Ridership and Impact on the City

The metro's growth has been steep. Ridership in the first months was limited by short operating hours and a partial route; the opening of the Motijheel section in November 2023, longer hours and rising train frequency then compounded month by month. The DMTCL figures reported in September 2026 put cumulative ridership at 313,546,306 since launch, with daily numbers "always above 450,000" and a single-day record of 499,756 on 10 September 2026. Motijheel, the business-district terminus, is the busiest station, averaging about 51,500 entries a day. Press reports of DMTCL's accounts describe ticket revenue rising from Tk 22 crore in the part-year of FY2022–23 to Tk 244 crore in FY2023–24 and roughly Tk 400 crore in FY2024–25, growth that has made the operating line, unusually for a new metro, a significant revenue earner, though the wider project accounts remain dominated by loan repayment.

The impact is easiest to see at street level. The corridor the metro serves, Uttara, Mirpur, Farmgate, Motijheel, is one of the most congested in a city where congestion has been estimated by the Policy Research Institute to cost on the order of 2.5 per cent of GDP in lost time and fuel. For office workers, students and the large number of women commuters who cite the metro's safety and predictability, the line has converted an unreliable two-hour road journey into a dependable 35-minute ride. It has not, by itself, decongested Dhaka: the metro's catchment is one corridor, buses and rickshaws still carry the overwhelming majority of trips, and the stations' surrounding streets remain crowded. But it has demonstrated, at scale, that Dhaka's residents will use modern public transport in very large numbers when it is offered, the premise on which the rest of the network is being justified.

The Network to Come: MRT-1 and MRT-5

MRT Line 1 is the network's most ambitious project: at about 31 kilometres it combines a 19.87-kilometre underground line from Hazrat Shahjalal International Airport to Kamalapur, Bangladesh's first underground metro, with an 11.37-kilometre elevated branch from Natun Bazar to the Purbachal New Town. Construction was inaugurated in February 2023, but for more than three years work was largely confined to the depot at Purbachal, land and utility works. The position changed in autumn 2026. On 16 September 2026 ECNEC approved a revised cost of Tk 1,14,394 crore for the line, and on 27 October 2026 DMTCL signed the main construction contracts for its elevated sections, stations and systems. The original target of completion by December 2026 has been abandoned, officials conceded in 2025 that the line would take at least three to four additional years, and completion is now expected in 2033.

MRT Line 5 (Northern Route) will be Dhaka's first east–west line, running 20 kilometres from Hemayetpur, near Savar, to Vatara, with 14 stations, nine underground and five elevated, and an interchange with MRT-6 at Mirpur 10. Its revised cost, Tk 89,848 crore, was approved by ECNEC on the same day as Line 1's, with an implementation period running to December 2032. The most advanced element is the Hemayetpur depot, whose land development was reported 87.54 per cent complete as of October 2026; on 27 October 2026 contracts were also signed for the depot buildings and for the line's 6.5 kilometres of elevated track and five elevated stations, while the underground central section is still to be contracted. Project documents forecast about 1.23 million passengers a day for the line. Both Line 1 and Line 5 are financed jointly by the government and JICA. Beyond them, MRT Line 5's Southern Route, MRT-2 and MRT-4 remain at planning stage, as the finance minister confirmed in the June 2026 budget speech.

Criticisms and Challenges

The metro's success with passengers has not exempted it from criticism, most of it aimed at cost and delay. Transport analysts have long noted that MRT-6's cost per kilometre, about Tk 1,574 crore, is high by regional standards, and the escalation from Tk 21,985 crore to Tk 32,718 crore has been repeatedly questioned in the press. The concern has sharpened with the new lines: a February 2026 analysis reported that Lines 1 and 5 are estimated at about Tk 3,618 crore per kilometre, more than double Line 6's unit cost, and quoted DMTCL's own managing director among those attributing the inflation partly to financing conditions that restrict competition among contractors. Defenders reply that underground construction in a dense deltaic city, extensive land acquisition and a weak taka explain much of the difference, but the combined Tk 2,04,242 crore price of Lines 1 and 5 North has made the affordability of the full network a live political question.

Delay is the second charge. Kamalapur's opening has moved from June 2025 to an expected July 2027; MRT-1 has slipped from a 2026 target to 2033. The third is crowding: even at today's frequencies, peak-hour trains on MRT-6 fill to capacity, and reporting since 2024 has documented passengers at busy stations such as Farmgate, Mirpur 10 and Motijheel unable to board. The system has also had to absorb shocks: during the unrest of July 2024 the Mirpur 10 and Kazipara stations were vandalised and remained closed for months. Finally, there is a standing debate about who the metro serves: at Tk 20–100, fares are several times the cost of a bus ride, and critics argue the network's benefits skew towards middle-income commuters while its costs are carried by all taxpayers. DMTCL's response, that time savings, safety and reliability justify the premium, and that ridership figures prove the demand, is borne out by the queues, but the argument will follow every new line.

What is not in doubt is the direction of travel. Dhaka set out in 2005 to build a metro network, opened its first line seventeen years later, and has since watched that line fill to its design capacity. The questions that will decide the metro's place in the city's history are now the practical ones: whether Kamalapur opens on its latest date, whether Lines 1 and 5 can be built closer to their revised budgets than Line 6 was to its original, and whether a network planned for 2035 can arrive in time for the city the United Nations expects to be the world's largest within a generation. On the evidence of MRT-6's first four years, the passengers, at least, are ready.